• You must be logged in to see or use the Shoutbox. Besides, if you haven't registered, you really should. It's quick and it will make your life a little better. Trust me. So just register and make yourself at home with like-minded individuals who share either your morbid curiousity or sense of gallows humor.
www.yahoo.com/news/latest-students-hold-vigil-bridge-collapse-victims-153828102.html

5:20 p.m.

Federal investigators say they've confirmed that workers were adjusting a tension rod on a newly installed portion of a pedestrian bridge when it collapsed on a busy highway, killing six people.

The National Transportation Safety Board on Wednesday said that workers were adjusting a second tension rod on the north end of the span last week after having done the same on the south end just before.

When completed, the bridge was to span a highway and canal and connect Florida International University's campus to the neighboring community of Sweetwater.

The board said it is also removing bridge components for further testing. All of them are from the north end of the structure, including portions of the walkway's canopy, floor and vertical and diagonal support pieces.

___

11:35 a.m.

Hundreds of Florida International University students gathered for a vigil Wednesday morning for the six victims of a pedestrian bridge collapse near their campus.

The names of the victims were displayed on a screen inside a ballroom on the Miami-area campus. Loud gasps and crying could be heard from the crowd when the name of FIU student Alexa Duran appeared on the screen.

FIU President Mark Rosenberg said the school remained in deep shock over the collapse Thursday of the 950-ton (860-metric ton) structure onto a busy roadway.

The bridge was intended to connect the campus with the neighboring city of Sweetwater. Mayor Orlando Lopez said the construction project aimed to save lives but ended in tragedy.

___

11:30 p.m.

Documents show construction of a Miami area pedestrian bridge that collapsed and killed six people was behind schedule and millions over budget amid a key design change involving the placement of one of its support towers.

The documents obtained by The Associated Press show the Florida Department of Transportation in October 2016 advised Florida International University and its contractors to move one of the bridge's main support structures 11 feet (3 meters) north to the edge of a canal, requiring some new structural design.

The span's signature, 109-foot-tall (33-meter-tall) pylon was to be built atop a base at the span's northern end. Videos of Thursday's collapse show a prefabricated concrete segment of the bridge began crumbling on the same end of the span where the tower redesign occurred.
 
https://www.miamiherald.com/news/local/community/miami-dade/article218594530.html
The contractors who designed and built the disastrous Florida International University bridge have been cited by federal authorities for several “serious” worker-safety violations and face tens of thousands of dollars in fines.

The companies failed to provide workers with a proper safety line and did not remove them from the area despite the bridge developing cracks of “significant width, depth and length at critical locations,” according to a series of citations released Tuesday by the Occupational Safety and Health Administration (OSHA).

The FIU pedestrian bridge collapsed March 15 while it was still under construction over Southwest Eighth Street, killing five motorists below and a worker, Navaro Brown, who had been standing atop the span. An additional five workers were seriously injured, including one, Kevin Hanson, who sustained a serious brain injury and went into a lengthy coma.
[....]
OSHA cited five companies for seven worker-safety violations, fining them a total of $86,658 in proposed penalties. The companies are designer FIGG Bridge Engineers; builder Munilla Construction Management; Bolton Perez & Associates, which provided engineering and inspection services; Structural Technologies, which specializes in post-tensioning work on bridges; and a concrete contractor, the Structural Group of South Florida. (That last company, based in Homestead, doesn’t appear to be connected in corporate records to Structural Technologies, a national firm.)

“Collectively, these employers failed to take appropriate action and provide the necessary protections to their employees while they were working on the bridge on the day it collapsed,” OSHA regional administrator Kurt A. Petermeyer said in a statement.

OSHA, which is part of the U.S. Department of Labor, described the citations as “serious” violations.

They mark the first punishments handed down for the deadly accident, although more may follow. The National Transportation Safety Board is investigating the cause of the collapse, a process that likely will take months. Ultimately, a criminal case remains possible, depending on the NTSB’s findings, although Florida law may shield the companies from being charged, legal experts say. Several civil lawsuits are ongoing.

The companies have 15 business days to accept the citations, schedule a conference with OSHA or contest the findings, according to the agency.

Michael Hernández, a spokesman for MCM, provided the following statement: “MCM views OSHA’s action as a positive first step toward understanding the root cause of this tragic accident. While MCM is still reviewing the OSHA fall protection citation, it is noteworthy that OSHA has not claimed that the cited conditions had anything to do with the FIU bridge span’s failure.”

The other contractors did not respond to requests for comment. Neither did FIU.

FIGG and Bolton Perez were each cited for not evacuating their workers from the bridge, which had begun to develop cracks even before it was swung into place across the busy road on March 10. OSHA said the cracks “compromised the structural integrity of the bridge,” although a FIGG engineer left a voice mail for the Florida Department of Transportation saying the cracks were not a safety threat days before the collapse. The agency said employees should have been removed from the “zone of danger” until the bridge was temporarily shored up at the north end where the cracks appeared.

In addition, OSHA cited the Structural Group of South Florida because employees were using a safety line “that was not tensioned and was laying on the deck of the bridge canopy,” instead of being placed above the workers. MCM and Structural Technologies were also cited for that violation, as well as for attaching five employees to a single, improperly installed line, exposing them to dangerous falls.

When the bridge collapsed at 1:47 p.m., the workers came crashing down, too.

Brown, a 37-year-old from Jamaica, worked for Structural Technologies. He died at a local hospital after being rescued from the rubble by first responders. Hanson also worked for Structural Technologies. His family took to the Internet to raise nearly $20,000 after he went into a coma. He has since regained consciousness.

Brown and the other workers were on top of the bridge to tighten, or re-tension, rods running through the span that strengthened the structure. Who gave the order to send them up there — and who decided to keep the road open while construction work was being performed — remain unclear. It’s possible the work was being performed to tighten the alarming cracks that had been opening in the bridge.

A meeting was held the morning of the collapse to discuss the cracks but FDOT refused to release minutes from the meeting, citing NTSB instructions. The Miami Herald is suing the department to compel their release.

The bridge’s design suffered from a calculation error that may have weakened it at a key connection point where the cracks developed, according to independent engineering experts consulted by the Herald. That weakness may have led to the collapse, the engineers said.
 
How are there design errors? Does no one check this shit before it's built? No agency is in charge of making sure structures will be secure?
 
How are there design errors? Does no one check this shit before it's built? No agency is in charge of making sure structures will be secure?

I'd say it's the same kind of bureaucracy that allowed Boeing to self-certify the new systems in their 737-Max.

Look how that turned out...
 